CTGR Qinghai Golmud 100MW
Plant |
CTGR Qinghai Golmud 100MW |
Location |
Golmud,
Wutumeiren, |
Capacity (MW) |
100MW |
Construction Start Date |
2023 |
Construction End Date |
Under construction |
Generation Start Year |
plan: 2024 |
Heliostat Aperture Area (m²) |
115 |
Heliostat Dimension |
area(115.75m^2) |
Heliostat Facets (C x R) |
5x7 |
Solar Field Area (m²) |
747500 |
Receiver Fluid |
Molten Salt |
Number of Heliostats |
6460 |
Tower Position (Lat/Long) |
36.83, 93.27 |
General Plant Data
· Location: Golmud, Wutumeiren, Haixi, Qinghai, China
· Capacity (MW): 100MW
Plant Timeline
· Construction Start Date: 2023
· Construction End Date: Under construction
· Generation Start Year: plan: 2024
Plant Costs
Heliostat Design
· Heliostat Aperture Area (m²): 115
· Heliostat Dimension: area(115.75m^2)
· Heliostat Facets (C x R): 5x7
· Solar Field Area (m²): 747500
Source: http://www.cnste.org/html/xiangmu/2023/1129/11800.html
Tower/Receiver
· Receiver Fluid: Molten Salt
Plant Layout
· Number of Heliostats: 6460
· Tower Position (Lat/Long): 36.83, 93.27
Other Sources:
[1] “CTGR
Qinghai Golmud100MW Tower + 1000MW PV | Concentrating Solar Power Projects |
NREL.” Solarpaces.nrel.gov,
solarpaces.nrel.gov/project/ctgr-qinghai-golmud100mw-tower-1000mw-pv.
Link: https://solarpaces.nrel.gov/project/ctgr-qinghai-golmud100mw-tower-1000mw-pv