GENERATION PLANTS

 

 

CTGR Qinghai Golmud 100MW

Plant

CTGR Qinghai Golmud 100MW

Location

Golmud, Wutumeiren,
Haixi,
Qinghai, China

Capacity (MW)

100MW

Construction Start Date

2023

Construction End Date

Under construction

Generation Start Year

plan: 2024

Heliostat Aperture Area (m²)

115

Heliostat Dimension

area(115.75m^2)

Heliostat Facets (C x R)

5x7

Solar Field Area (m²)

747500

Receiver Fluid

Molten Salt

Number of Heliostats

6460

Tower Position (Lat/Long)

36.83, 93.27

General Plant Data

·         Location: Golmud, Wutumeiren, Haixi, Qinghai, China

·         Capacity (MW): 100MW

Plant Timeline

·         Construction Start Date: 2023

·         Construction End Date: Under construction

·         Generation Start Year: plan: 2024

Plant Costs

Heliostat Design

·         Heliostat Aperture Area (m²): 115

·         Heliostat Dimension: area(115.75m^2)

·         Heliostat Facets (C x R): 5x7

·         Solar Field Area (m²): 747500

A picture containing sky, outdoor, transport, power shovel

Description automatically generated

Source:  http://www.cnste.org/html/xiangmu/2023/1129/11800.html

Tower/Receiver

·         Receiver Fluid: Molten Salt

Plant Layout

·         Number of Heliostats: 6460

·         Tower Position (Lat/Long): 36.83, 93.27

 

 

 

Other Sources:

[1] “CTGR Qinghai Golmud100MW Tower + 1000MW PV | Concentrating Solar Power Projects | NREL.” Solarpaces.nrel.gov, solarpaces.nrel.gov/project/ctgr-qinghai-golmud100mw-tower-1000mw-pv.

Link: https://solarpaces.nrel.gov/project/ctgr-qinghai-golmud100mw-tower-1000mw-pv